Construction
Progress.

At Wollert Rise, construction is in full swing, meaning life on nature’s doorstep is closer than you think. Come on this journey with us by keeping track of works completed below.
Or, see the Birds iView

Stage 1

Construction Commenced

June 2021

Estimated title due

Q1 2023

Estimated settlement due

Q1 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 2

Construction Commenced

June 2021

Estimated title due

Q1 2023

Estimated settlement due

Q1 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 3

Construction Commenced

June 2021

Estimated title due

Q1 2023

Estimated settlement due

Q1 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 5

Construction Commenced

November 2021

Estimated title due

Q2 2023

Estimated settlement due

Q2 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 6

Construction Commenced

November 2021

Estimated title due

Q2 2023

Estimated settlement due

Q2 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed