Construction
Progress.

At Wollert Rise, construction is in full swing, meaning life on nature’s doorstep is closer than you think. Come on this journey with us by keeping track of works completed below.
Or, see the Birds iView

Stage 1

Construction Commenced

June 2021

Estimated title due

November 2023

Estimated settlement due

November 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 2

Construction Commenced

June 2021

Estimated title due

November 2023

Estimated settlement due

November 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 2B

Estimated title due

Mid 2025

Estimated settlement due

Mid 2025

  1. In progress Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 3

Construction Commenced

June 2021

Estimated title due

November 2023

Estimated settlement due

November 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 4

Estimated title due

Mid-2024

Estimated settlement due

Mid-2024

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. In progress Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 5

Construction Commenced

November 2021

Estimated title due

November 2023

Estimated settlement due

November 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 6

Construction Commenced

November 2021

Estimated title due

November 2023

Estimated settlement due

November 2023

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 7

Estimated title due

Q3 2024

Estimated settlement due

Q3 2024

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 8

Estimated title due

Q3 2024

Estimated settlement due

Q3 2024

  1. 100% Plans & Permit 1
  2. 100% Earthworks 1
  3. In progress Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 9

Estimated title due

Mid 2025

Estimated settlement due

Mid 2025

  1. In progress Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 10

Estimated title due

Mid 2025

Estimated settlement due

Mid 2025

  1. In progress Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 11

Estimated title due

Mid 2025

Estimated settlement due

Mid 2025

  1. In progress Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed

Stage 13

Estimated title due

Mid 2025

Estimated settlement due

Mid 2025

  1. In progress Plans & Permit 1
  2. 100% Earthworks 1
  3. 100% Sewer and Drainage 1
  4. 100% Road Boxing, Kerb and Channel 1
  5. 100% Electrical and Communication Supply 1
  6. 100% Footpaths, Asphalt and Line making 1
  7. 100% Completion and Inspection of works 1
  8. 100% Titles and Settlements 1
  1. 100% Statement of Compliance Issued 1
  2. 100% Plan of Subdivision Lodged 1
  3. 100% Titles Released 1
  4. 100% Settlement 1
Civil - % Completed
Registration - % Completed